Q1. Which Concrete mix using currently at your site and also how much qty of cement & fine aggregate and coarse aggregate in that ?
We are currently using M25 grade concrete mix at our site with a ratio of 1:1:2 (cement:fine aggregate:coarse aggregate).
M25 grade concrete mix is being used at our site
The ratio of the mix is 1:1:2 (cement:fine aggregate:coarse aggregate)
For example, for 1 cubic meter of M25 concrete mix, we use 350 kg of cement, 700 kg of fine aggregate, and 1400 kg of coarse aggregate
Q2. How do you calculate man power for work ?
Man power for work can be calculated by estimating the amount of work to be done, the time required to complete it, and the efficiency of the workers.
Estimate the amount of work to be done
Determine the time required to complete the work
Consider the efficiency of the workers
Calculate the total man hours needed by dividing the total work by the productivity rate of the workers
Q3. 2. What are the safety precaution required for height work?
Safety precautions for height work include proper training, use of personal protective equipment, and secure anchorage points.
Ensure workers are properly trained and certified for the specific task
Use appropriate personal protective equipment such as harnesses, helmets, and safety glasses
Ensure secure anchorage points are available and used properly
Regularly inspect equipment and replace any damaged or worn components
Implement a rescue plan in case of emergency
Consider weathe...read more
Q4. What is the productivity of one carpenter & 1 bar bender ?
Productivity of one carpenter & 1 bar bender depends on the type of work and skill level.
Productivity can vary based on the complexity of the task assigned.
A skilled carpenter may be able to complete tasks faster than an inexperienced one.
Efficiency of tools and equipment can also impact productivity.
On average, a carpenter can complete 8-12 square meters of formwork per day, while a bar bender can bend around 200-300 bars per day.
Q5. What is the co-efficient of tile adhesive for wall cladding ?
The co-efficient of tile adhesive for wall cladding is typically around 0.5 to 0.7.
The co-efficient of tile adhesive refers to the amount of adhesive needed to secure a certain area of wall cladding.
It is usually recommended to follow the manufacturer's instructions for the specific type of tile adhesive being used.
The co-efficient can vary based on factors such as the type of tiles, substrate, and environmental conditions.
For wall cladding, the co-efficient is typically in t...read more
Q6. How to control labor and Matireal wastage
Labor and material wastage can be controlled through proper planning, monitoring, and training.
Implement lean manufacturing principles to reduce waste in production processes
Regularly monitor and analyze production data to identify areas of improvement
Train employees on efficient use of materials and proper handling techniques
Utilize inventory management systems to track material usage and minimize overstocking
Implement quality control measures to reduce defects and rework
Est...read more
Q7. Lap zones in beams and columns, steel margin in footings
Lap zones in beams and columns ensure proper reinforcement overlap for structural integrity. Steel margin in footings provides additional strength and safety.
Lap zones in beams and columns refer to the area where reinforcement bars overlap to ensure proper load transfer and structural integrity
Steel margin in footings refers to the additional steel reinforcement provided in footings to enhance strength and safety
Proper detailing and calculation of lap zones and steel margin a...read more
Q8. What are the indirect cost of a project ?
Indirect costs of a project are expenses not directly related to the specific project activities.
Indirect labor costs (e.g. supervision, support staff)
Indirect materials costs (e.g. consumables, tools)
Indirect expenses (e.g. utilities, rent)
Overhead costs (e.g. administrative expenses)
Insurance costs
Taxes
Q9. What is the work at height hazard with precautions
Work at height hazard refers to the risk of falling from elevated surfaces. Precautions include using fall protection equipment, proper training, and regular safety inspections.
Use appropriate fall protection equipment such as harnesses, guardrails, and safety nets
Ensure workers are properly trained on how to use the equipment and follow safety procedures
Conduct regular safety inspections of the work area to identify and address any potential hazards
Implement a permit-to-work...read more
Q10. Grades of concrete and strengths
Grades of concrete are classified based on their compressive strength. Common grades include M10, M20, M30, etc.
Concrete grades are denoted by the letter 'M' followed by a number, representing the compressive strength in megapascals (MPa)
For example, M20 concrete has a compressive strength of 20 MPa
Higher grade concrete like M30 or M40 is used for structures requiring higher strength
Lower grade concrete like M10 is used for non-structural purposes
Q11. What is the unit of skirting ?
The unit of skirting is typically measured in linear feet or meters.
Skirting is typically measured in linear feet or meters
It is used to cover the joint between the wall and the floor
Commonly used in construction and interior design projects
Q12. How to control accident?
Accidents can be controlled through proper safety measures and training.
Identify potential hazards and take steps to eliminate or minimize them
Provide proper safety equipment and ensure it is used correctly
Train employees on safe work practices and emergency procedures
Regularly inspect equipment and facilities for safety issues
Encourage reporting of near-misses and investigate them to prevent future accidents
Q13. Wastage of various materials
Wastage of materials in construction projects can occur due to poor planning, inaccurate measurements, mishandling, or theft.
Wastage can occur due to inaccurate measurements during cutting or shaping of materials.
Poor planning can lead to ordering excess materials that end up unused.
Mishandling of materials during transportation or storage can result in damage and wastage.
Theft of materials on construction sites is also a common cause of wastage.
Implementing proper inventory ...read more
Q14. Mode of measurement Billing steps
Mode of measurement billing steps involve determining the method of measurement and the corresponding billing process.
Mode of measurement refers to the specific rules and guidelines used to measure quantities of work done on a construction project.
Billing steps involve converting the measured quantities into monetary values based on the agreed rates and terms in the contract.
Common modes of measurement include SMM7, CESMM, and NRM.
Billing steps typically include taking off qu...read more
Q15. Why is safety important
Safety is important to prevent accidents, injuries, and illnesses in the workplace.
Ensures the well-being of employees
Reduces the risk of accidents and injuries
Increases productivity and morale
Compliance with regulations and laws
Protects company reputation and avoids financial losses
Q16. What is safety policy
Safety policy is a set of rules and guidelines implemented by an organization to ensure the safety and well-being of its employees.
Safety policy outlines the organization's commitment to safety and health in the workplace.
It includes procedures for identifying and addressing potential hazards.
Safety policy also defines roles and responsibilities for employees in maintaining a safe work environment.
Regular training and communication are essential components of a successful saf...read more
Q17. Current CTC and Expected CTC
Current CTC is $60,000 and Expected CTC is $70,000.
Current CTC is $60,000 per annum.
Expected CTC is $70,000 per annum.
The expected CTC includes a potential increase based on my experience and skills.
I am open to negotiation based on the overall compensation package offered.
Q18. Long run association with KMV
Long run association with KMV
I have been associated with KMV for a significant period of time
During my tenure at KMV, I have gained valuable experience and knowledge
I have developed strong relationships with colleagues and clients at KMV
My contributions to KMV have been recognized and rewarded
I have actively participated in KMV's growth and success
Top HR Questions asked in Apparel Resources
Interview Process at Apparel Resources
Top Interview Questions from Similar Companies
Reviews
Interviews
Salaries
Users/Month