I applied via Company Website and was interviewed before Jan 2021. There were 3 interview rounds.
Pumps and aerators are used to move fluids and gases respectively.
Pumps work by creating a pressure difference to move fluids from one place to another.
Aerators introduce air into liquids to increase oxygen levels and promote biological processes.
Types of pumps include centrifugal, positive displacement, and jet pumps.
Types of aerators include surface aerators, diffused aerators, and mechanical aerators.
I applied via Approached by Company and was interviewed before Apr 2021. There was 1 interview round.
posted on 23 Oct 2021
I applied via Company Website and was interviewed in May 2021. There were 3 interview rounds.
VCB and ACB transformers require regular maintenance to ensure optimal performance and prevent breakdowns.
Regular inspection of the transformer and its components
Cleaning of the transformer and its components
Checking and tightening of connections
Testing of protective devices
Replacement of worn out or damaged parts
Regular oil analysis
Following manufacturer's recommended maintenance schedule
Training of personnel on prope
I appeared for an interview before Feb 2021.
posted on 10 Dec 2022
I applied via Walk-in and was interviewed before Dec 2021. There were 3 interview rounds.
Detailed information about the previous company where i worked.Discussed with project manager regarding my roles and assignments i had taken on work location.Along with that we discussed about my academic projects and skills that i had mastered in my career
Interviewers gave me the task to elaborate the design of pollution control equipments and assessments
posted on 2 Mar 2022
I applied via Campus Placement and was interviewed before May 2022. There were 3 interview rounds.
MCQ based 50 marks 50 questions test.
I applied via Naukri.com and was interviewed in Mar 2021. There were 5 interview rounds.
I applied via Walk-in and was interviewed in Aug 2022. There was 1 interview round.
Precommissioning tests of transformers are essential to ensure their proper functioning.
Insulation resistance test
Turns ratio test
Vector group test
Winding resistance test
Magnetizing current test
No-load loss and excitation current test
Load loss and impedance voltage test
based on 1 interview
Interview experience
Assistant Manager
26
salaries
| ₹7.1 L/yr - ₹13 L/yr |
Deputy Manager
11
salaries
| ₹10 L/yr - ₹15 L/yr |
Senior Engineer
10
salaries
| ₹4.2 L/yr - ₹8.5 L/yr |
Manager
8
salaries
| ₹14.2 L/yr - ₹19 L/yr |
Engineer
7
salaries
| ₹3.5 L/yr - ₹6.8 L/yr |
Ion Exchange India
Re Sustainability Limited
DuPont
VA Tech Wabag