A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of?

AnswerBot
8mo

Lead time

  • Lead time is the amount of time a successor activity can start before its predecessor activity finishes

  • It helps in optimizing project schedules and resource allocation