Senior QS and Billing Engineer
Senior QS and Billing Engineer Interview Questions and Answers

Asked in Rohan Builders

Q. If a plot of 54.4 acres is given to you and excavation should happen in benching, how will you streamline the measurements of earthwork in cutting and filling?
I will divide the plot into smaller sections and calculate the volume of earthwork required for each section separately.
Divide the plot into smaller sections based on the topography and soil type
Calculate the volume of earthwork required for each section separately using the formula: Volume = Area x Depth
Aggregate the volumes of all sections to get the total volume of earthwork required
Use the total volume to estimate the cost of excavation and filling
Ensure that the excavati...read more

Asked in Rohan Builders

Q. How do you prepare a rolling reconciliation sheet for CEMENT, REINFORCEMENT STEEL, and STRUCTURAL STEEL?
Rolling reconciliation sheet for cement, reinforcement steel & structural steel
Collect data on the quantity and cost of cement, reinforcement steel, and structural steel used in the project
Prepare a table with columns for opening balance, receipts, issues, closing balance, and remarks for each material
Update the table regularly with the latest data and calculate the closing balance for each material
Compare the closing balance with the physical stock to identify any discrepanc...read more

Asked in Rohan Builders

Q. What are the deduction criteria for plastering measurements?
Deduction criteria for plastering measurements include openings, thickness, and wastage.
Openings such as doors and windows are deducted from the total area of plastering.
Thickness of plastering is also taken into consideration for deductions.
Wastage due to uneven surfaces or improper mixing is also deducted.
Deductions are calculated as per the standard measurement practices and contract specifications.
For example, if the contract specifies a deduction of 5% for wastage, then ...read more

Asked in SRR Projects

Q. What documents are required for client billing?
Documents required for client billing include contract agreement, work completion report, and invoice.
Contract agreement outlining scope of work and payment terms
Work completion report detailing completed tasks and milestones
Invoice with breakdown of costs and payment schedule

Asked in SRR Projects

Q. Describe the rate analysis process.
Rate analysis process involves calculating the rates of various items in a construction project.
Rate analysis involves breaking down the cost of materials, labor, equipment, and overhead for each item in a project.
It helps in determining the unit rate for each item based on the quantities and costs involved.
Factors such as market rates, location, project complexity, and profit margin are considered in rate analysis.
Rate analysis is essential for accurate cost estimation, budg...read more

Asked in SRR Projects

Q. Do you know what a bar bending schedule is?
Yes, a Bar Bending Schedule (BBS) is a document that provides details of reinforcement steel bars required for construction.
A Bar Bending Schedule (BBS) includes information on bar sizes, quantities, shapes, and bending dimensions.
It is essential for ensuring the correct placement and quantity of reinforcement bars in a structure.
BBS helps in estimating the total quantity of steel required for a project and assists in cost estimation.
Example: BBS for a column will specify the...read more

Asked in Capacit'e Infraprojects

Q. Nature and behavior of individual
Individual's nature and behavior are crucial for success in any role.
Positive attitude towards work and colleagues
Good communication and interpersonal skills
Ability to work under pressure and meet deadlines
Attention to detail and accuracy
Adaptability and willingness to learn
Honesty and integrity
Professionalism and work ethics