Planning Engineer
20+ Planning Engineer Interview Questions and Answers for Freshers
Q1. Oil and Gas construction activities from civil, piping, Equipment etc .
Oil and gas construction activities involve civil, piping, and equipment work.
Civil work includes building foundations, roads, and drainage systems.
Piping work involves installing pipelines for oil and gas transportation.
Equipment work includes installing and commissioning various types of equipment such as pumps, compressors, and turbines.
Other activities include electrical and instrumentation work, testing and commissioning, and project management.
Examples of oil and gas co...read more
Q2. How to track a project on daily basis in Primavera P6
To track a project in Primavera P6 on a daily basis, use the following steps.
Update progress for each activity daily
Review critical path activities regularly
Monitor resource allocation and availability
Compare planned vs. actual progress
Generate daily reports for stakeholders
Q3. How could you manage fund flow during project through your work plan.
I would create a detailed budget and cash flow plan to track expenses and ensure funds are available when needed.
Develop a comprehensive project budget that includes all expenses
Create a cash flow plan to track when funds will be needed and ensure they are available
Regularly monitor expenses and adjust the cash flow plan as needed
Communicate with stakeholders to ensure they are aware of funding needs and any potential issues
Consider alternative funding sources if necessary
Q4. Whats of views in ,when creating material ?
Views in creating material include cost, quality, availability, and sustainability.
Consider cost implications of materials chosen
Ensure quality meets project requirements
Check availability of materials in required quantities
Evaluate sustainability aspects of materials used
Q5. What are child part anad standard items
Child parts are components that make up a larger item, while standard items are pre-designed parts used in multiple products.
Child parts are used to create a larger item, such as a car engine being made up of multiple components.
Standard items are pre-designed parts that are used in multiple products, such as screws or bolts.
Child parts can be customized or modified to fit specific needs, while standard items are typically mass-produced and not customizable.
Q6. How many types of material are there
There are countless types of materials, ranging from natural to synthetic, organic to inorganic, and metals to plastics.
Materials can be classified based on their composition, properties, and usage.
Some common types of materials include metals, ceramics, polymers, composites, and semiconductors.
Natural materials include wood, stone, and animal products, while synthetic materials include plastics and synthetic fibers.
Materials can also be classified based on their physical pro...read more
Share interview questions and help millions of jobseekers 🌟
Q7. how to make Contract for vendors
A contract for vendors should clearly define the scope of work, payment terms, delivery schedule, quality standards, and dispute resolution mechanisms.
Define the scope of work and deliverables
Specify the payment terms and schedule
Set quality standards and acceptance criteria
Include provisions for warranties and guarantees
Outline the dispute resolution mechanisms
Include clauses for termination and breach of contract
Ensure compliance with legal and regulatory requirements
Provid...read more
Q8. How do you manage procurement schedule
I manage procurement schedule by creating a detailed plan, tracking progress, identifying risks, and communicating with stakeholders.
Create a detailed procurement schedule outlining key milestones and deadlines
Track progress regularly to ensure tasks are completed on time
Identify potential risks and develop contingency plans to mitigate them
Communicate effectively with suppliers, team members, and stakeholders to ensure alignment and address any issues
Regularly review and upd...read more
Planning Engineer Jobs
Q9. How to calculate number of tiles
Number of tiles can be calculated by determining the area to be covered and the size of each tile.
Calculate the total area to be covered by multiplying the length and width of the space.
Determine the size of each tile in square units.
Divide the total area by the size of each tile to get the number of tiles needed.
Consider adding extra tiles for cuts and wastage.
For example, if a room is 10 feet by 12 feet and each tile is 1 square foot, you would need 120 tiles.
Q10. How to calculate weight of steel
Weight of steel can be calculated by multiplying the volume of steel by its density.
Calculate the volume of steel (length x width x height)
Determine the density of the specific type of steel being used
Multiply the volume by the density to get the weight
Example: Weight of a steel plate with dimensions 2m x 1m x 0.1m and density of 7850 kg/m^3 would be 2 x 1 x 0.1 x 7850 = 1570 kg
Q11. how many cavities are there
The question is unclear and lacks context. Please provide more information.
Please provide more context or specify what type of cavities you are referring to.
Are you asking about cavities in a building or in a human body?
Without more information, it is impossible to answer this question accurately.
Q12. How many types of gate
There are several types of gates used in construction projects.
Swing gate
Sliding gate
Rolling gate
Barrier gate
Turnstile gate
Vertical pivot gate
Bi-folding gate
Cantilever gate
Q13. How many plastic material
The question is unclear and lacks context. Please provide more information.
Please clarify the context of the question.
Are you asking about the types of plastic materials available?
Or are you asking about the quantity of plastic materials needed for a project?
Without more information, it is difficult to provide a specific answer.
Q14. how to do Progress payment
Progress payment is a payment made to a contractor based on the percentage of work completed.
Determine the percentage of work completed
Agree on the payment schedule with the contractor
Verify the work completed before making the payment
Ensure the payment is made on time to avoid delays
Keep accurate records of progress payments made
Q15. Explain the piping iso drawings
Piping iso drawings are detailed engineering drawings that show the layout of piping systems in a plant or facility.
Piping iso drawings provide a detailed view of the piping system, including the size and type of pipes, valves, fittings, and other components.
They are used by engineers and designers to plan and design piping systems, and by construction and maintenance teams to install and maintain the system.
The drawings are typically created using computer-aided design (CAD)...read more
Q16. Path enterprise structure one by one
Path enterprise structure involves defining the hierarchy of business units, departments, and reporting relationships within an organization.
Start with the top-level entity, usually the company or organization itself
Identify the major divisions or business units within the organization
Break down each division into departments or functional areas
Establish reporting relationships between different levels of the structure
Consider any subsidiaries or affiliated entities that are ...read more
Q17. What is baseline schedule
Baseline schedule is the original project schedule used as a reference point for comparison.
Baseline schedule is the initial approved project schedule that serves as a benchmark for measuring project progress.
It includes the planned start and finish dates for project activities, milestones, and deliverables.
Any changes to the schedule must be compared against the baseline schedule to assess impact.
Baseline schedule helps in tracking deviations, identifying delays, and managin...read more
Q18. What is critical path
Critical path is the longest sequence of tasks in a project that must be completed on time to ensure the project finishes on schedule.
Critical path helps in identifying the tasks that are crucial for the project timeline.
It determines the shortest possible duration for completing the project.
Any delay in tasks on the critical path will directly impact the project's overall timeline.
Activities on the critical path have zero slack or float.
Example: In a construction project, ta...read more
Q19. what is WBS
WBS stands for Work Breakdown Structure, a hierarchical decomposition of project deliverables into smaller, manageable components.
WBS is a tool used in project management to organize and define the scope of a project
It breaks down the project into smaller, more manageable components
Each component is then assigned a unique identifier and can be further broken down into smaller components
WBS helps in estimating project costs, scheduling, and resource allocation
Example: WBS for ...read more
Q20. What's of sap mm ?
SAP MM stands for Materials Management, a module in SAP ERP system that manages procurement and inventory functions.
SAP MM helps in managing materials procurement, inventory management, and invoice verification processes.
It integrates with other modules like SAP SD (Sales and Distribution) and SAP PP (Production Planning).
SAP MM streamlines the procurement process by automating purchase orders, goods receipt, and invoice verification.
It helps in optimizing inventory levels an...read more
Q21. What is torque?
Torque is a measure of the rotational force applied to an object.
Torque is calculated by multiplying the force applied by the distance from the axis of rotation.
It is measured in units of force times distance, such as Newton-meters (Nm) or foot-pounds (ft-lb).
Torque is essential in determining the ability of a force to rotate an object.
Examples of torque include tightening a bolt with a wrench or opening a door with a handle.
Q22. Role of planning engineer
Planning engineers are responsible for creating project schedules, monitoring progress, and ensuring timely completion.
Develop project schedules using software like Primavera P6
Monitor project progress and identify potential delays
Coordinate with various teams to ensure timely completion
Prepare reports on project status and communicate with stakeholders
Implement changes to the schedule as needed to keep the project on track
Q23. Baselines in Primavera?
Baselines in Primavera are snapshots of the project schedule at a specific point in time, used for comparison and tracking progress.
Baselines capture the original project plan before any changes are made.
They are used as a reference point to compare actual progress against planned progress.
Baselines help in identifying deviations from the original plan and taking corrective actions.
In Primavera, baselines can be created for the entire project or specific activities.
They are e...read more
Q24. What is lead time
Lead time is the amount of time it takes for a process to be completed from start to finish.
Lead time includes all the time spent on a task, including waiting time, processing time, and transportation time.
It is important in project management to accurately estimate lead times to ensure projects are completed on time.
For example, in construction, lead time may include the time it takes to order materials, receive them, and complete the project.
Q25. Density of steel
Density of steel is approximately 7.85 g/cm^3.
The density of steel is commonly expressed in grams per cubic centimeter (g/cm^3).
The density of steel is approximately 7.85 g/cm^3.
Different types of steel may have slightly different densities.
Interview Questions of Similar Designations
Interview experiences of popular companies
Calculate your in-hand salary
Confused about how your in-hand salary is calculated? Enter your annual salary (CTC) and get your in-hand salary
Reviews
Interviews
Salaries
Users/Month