Assistant Highway Engineer

Assistant Highway Engineer Interview Questions and Answers for Freshers

Updated 9 Apr 2024

Q1. What should be the maximum speed of paver during DBM LAYING?

Ans.

The maximum speed of paver during DBM laying should be around 2-3 km/h to ensure proper compaction and quality of the road surface.

  • The maximum speed of the paver should be controlled to allow for proper compaction of the DBM layer.

  • Excessive speed can lead to inadequate compaction, resulting in a weaker road surface and potential future issues.

  • A speed of 2-3 km/h is generally recommended for DBM laying to achieve optimal compaction and quality.

  • It is important for the operator ...read more

Q2. What is the maximum thickness of a layer?

Ans.

The maximum thickness of a layer in highway engineering is typically around 300 mm.

  • Maximum thickness is usually limited to around 300 mm for practical and cost-effective reasons

  • Thicker layers may lead to excessive settlement or instability

  • Thinner layers may not provide adequate strength or durability

  • Examples: Base course layer in flexible pavement is typically around 150-300 mm thick

Q3. What is laying temprature for DBM?

Ans.

The laying temperature for DBM (Dense Bituminous Macadam) typically ranges from 140 to 160 degrees Celsius.

  • Laying temperature for DBM is crucial for achieving proper compaction and bonding of the material.

  • The temperature range of 140-160 degrees Celsius ensures that the DBM is workable and can be compacted effectively.

  • Excessive heat can lead to premature cooling and inadequate compaction, while lower temperatures may result in poor bonding and durability.

  • It is important to mo...read more

Q4. What is the maximum speed of a compactor

Ans.

The maximum speed of a compactor varies depending on the type and model, but typically ranges from 2 to 6 miles per hour.

  • The maximum speed of a compactor is usually between 2 to 6 miles per hour.

  • The speed can vary based on the type of compactor (e.g. vibratory, smooth drum) and the model.

  • Higher speed compactors are often used for larger projects where efficiency is key.

  • Lower speed compactors are used for more precise compaction in smaller areas.

Are these interview questions helpful?

Q5. What is required slum for PQC?

Ans.

Slump is the required consistency of PQC (Pavement Quality Concrete) for proper construction.

  • The required slump for PQC typically ranges from 20-40 mm.

  • Slump test should be conducted at the site to ensure the correct consistency.

  • Proper slump ensures good workability and strength of the concrete.

  • If the slump is too high, it may lead to segregation and bleeding issues.

  • If the slump is too low, it may result in difficulty in placing and compacting the concrete.

Assistant Highway Engineer Jobs

Assistant Highway Engineer 1-3 years
MAV Associates
3.5
Rishikesh
Assistant Highway Engineer 1-3 years
MAV Associates
3.5
Supaul
Assistant Highway Engineer 1-3 years
MAV Associates
3.5
Mahur
Interview Tips & Stories
Ace your next interview with expert advice and inspiring stories

Calculate your in-hand salary

Confused about how your in-hand salary is calculated? Enter your annual salary (CTC) and get your in-hand salary

Assistant Highway Engineer Interview Questions
Share an Interview
Stay ahead in your career. Get AmbitionBox app
qr-code
Helping over 1 Crore job seekers every month in choosing their right fit company
65 L+

Reviews

4 L+

Interviews

4 Cr+

Salaries

1 Cr+

Users/Month

Contribute to help millions

Made with ❤️ in India. Trademarks belong to their respective owners. All rights reserved © 2024 Info Edge (India) Ltd.

Follow us
  • Youtube
  • Instagram
  • LinkedIn
  • Facebook
  • Twitter