I have 3 years of experience working in a packaging company where I managed a team and ensured efficient packaging processes.
Managed a team of packaging staff to ensure timely completion of orders
Implemented new packaging techniques to improve efficiency
Maintained inventory of packaging materials to prevent delays
Collaborated with suppliers to source high-quality packaging materials
I applied via Naukri.com and was interviewed before Jun 2023. There was 1 interview round.
To lead a team towards achieving company goals through strategic planning, effective communication, and continuous development.
Develop and implement strategic plans to achieve company objectives
Provide clear direction and support to team members
Continuously assess and improve team performance
Stay updated on industry trends and adapt strategies accordingly
posted on 26 Oct 2024
I was interviewed before Oct 2023.
I applied via Recruitment Consulltant and was interviewed before Jul 2022. There were 3 interview rounds.
posted on 24 May 2024
I applied via Recruitment Consulltant and was interviewed before May 2023. There was 1 interview round.
Wastewater technology
I applied via Referral and was interviewed in Jun 2022. There were 2 interview rounds.
I was interviewed before May 2016.
I have strong leadership and communication skills that are better suited for a non-technical role.
I excel in managing teams and resolving conflicts
I have a knack for strategic planning and decision-making
I enjoy interacting with customers and providing excellent service
posted on 25 Oct 2017
I was interviewed before Oct 2016.
Turbine erection alignment and commissioning procedure involves the process of aligning and commissioning a turbine for optimal performance.
Turbine erection alignment involves ensuring the turbine is properly aligned with the foundation and other components.
Commissioning procedure includes testing and verifying the functionality of the turbine.
Alignment is typically done using laser alignment tools to ensure precise po...
The turbine erection sequence refers to the specific order in which the components of a turbine are assembled and installed.
The foundation is prepared and the anchor bolts are installed.
The base frame is positioned and aligned with the anchor bolts.
The turbine tower sections are lifted and assembled on top of the base frame.
The nacelle, which houses the turbine's generator and other components, is installed on top of t...
I was interviewed before Mar 2017.
based on 1 interview
Interview experience
based on 13 reviews
Rating in categories
Senior Executive
72
salaries
| ₹0 L/yr - ₹0 L/yr |
Assistant Manager
56
salaries
| ₹0 L/yr - ₹0 L/yr |
Executive
27
salaries
| ₹0 L/yr - ₹0 L/yr |
Design Engineer
20
salaries
| ₹0 L/yr - ₹0 L/yr |
Service Engineer
20
salaries
| ₹0 L/yr - ₹0 L/yr |
ITW India
Knorr-Bremse
Gestamp
RAK Ceramics