i
Saint-Gobain
Filter interviews by
To sell glass, highlight its durability, versatility, and aesthetic appeal.
Emphasize the durability of glass, which can withstand high temperatures and resist scratches and stains.
Highlight the versatility of glass, which can be used for windows, mirrors, tabletops, and more.
Showcase the aesthetic appeal of glass, which can add elegance and sophistication to any space.
Provide examples of how glass can enhance the funct...
What people are saying about Saint-Gobain
posted on 1 Dec 2021
I applied via Company Website and was interviewed before Dec 2020. There were 3 interview rounds.
Micro planning of construction site involves detailed planning and scheduling of activities to ensure efficient and timely completion of the project.
It involves breaking down the project into smaller tasks and assigning timelines for each task.
It includes identifying the resources required for each task and ensuring their availability.
Micro planning also involves monitoring the progress of each task and making necessar...
The unit weight of 12mm bar depends on the type of steel used.
The unit weight of 12mm bar made of mild steel is 0.89 kg/m
For high tensile steel, the unit weight of 12mm bar is 1.06 kg/m
The density of steel used in the bar also affects the unit weight
I applied via Naukri.com and was interviewed in Mar 2022. There were 3 interview rounds.
I applied via Company Website and was interviewed before Jul 2023. There was 1 interview round.
I applied via Walk-in
The SOP (Standard Operating Procedure) of all works is a set of documented instructions that outline the steps to be followed for completing tasks.
SOPs provide consistency and ensure that tasks are performed correctly and efficiently.
They help in training new employees and serve as a reference guide for existing employees.
SOPs can cover various aspects such as safety procedures, quality control, maintenance, and troubl...
DLR stands for Detailed Project Report and DPR stands for Detailed Design Report. They are both important documents in engineering projects.
DLR is prepared before the start of a project and includes detailed information about the project scope, objectives, feasibility, and cost estimates.
DPR is prepared during the design phase of a project and provides detailed information about the design specifications, calculations,...
The quantity achieved is dependent on the manpower available.
The more manpower available, the higher the quantity that can be achieved.
Efficient utilization of manpower can lead to higher productivity.
Manpower shortage can result in lower quantity achieved.
Automation and technology can help in achieving higher quantity with less manpower.
Proper planning and coordination are essential to optimize manpower and achieve de
I applied via Company Website and was interviewed in Jan 2021. There were 3 interview rounds.
Lapping of beam is done by grinding the surface of the beam to achieve a smooth and flat finish.
The beam is placed on a lapping machine with an abrasive surface.
The machine moves the beam back and forth while the abrasive surface grinds away any imperfections.
The process is repeated with finer and finer abrasives until the desired finish is achieved.
Lapping can improve the strength and durability of the beam.
It is comm...
The number of cube samples taken for 60 cum of concrete depends on the specifications and requirements of the project.
The number of cube samples may vary depending on the project specifications and requirements.
Typically, 3 to 5 cube samples are taken for every 100 cubic meters of concrete.
The cube samples are taken to test the compressive strength of the concrete.
The number of cube samples may also depend on the locat...
After the shortlisting of CVs, list was sent for those who were eligible for the OT. The online test included aptitude + technical. There were pretty easy to moderate questions but time was less.
I applied via Referral and was interviewed in Jan 2024. There was 1 interview round.
The capacity of Tata Steel's lime plant is yet to be determined.
The capacity of the lime plant is currently unknown and is still to be decided by Tata Steel.
Tata Steel is likely in the process of determining the optimal capacity for their lime plant.
The capacity of the lime plant will depend on various factors such as production requirements, market demand, and technological capabilities.
based on 2 reviews
Rating in categories
Team Member
530
salaries
| ₹1.2 L/yr - ₹8.3 L/yr |
Software Engineer
171
salaries
| ₹3 L/yr - ₹11.4 L/yr |
Senior Software Engineer
165
salaries
| ₹6.5 L/yr - ₹24.1 L/yr |
Production Engineer
155
salaries
| ₹1 L/yr - ₹9.8 L/yr |
Key Account Manager
139
salaries
| ₹6.2 L/yr - ₹18 L/yr |
Tata Projects
Shapoorji Pallonji Group
Kalpataru Projects International
Nagarjuna Construction Company