The critical path is the longest sequence of tasks in a project that must be completed on time in order for the project to finish on schedule.
Identifying the critical path helps in determining the minimum time needed to complete a project.
It consists of tasks that have zero slack or float, meaning any delay in these tasks will delay the entire project.
Activities on the critical path are often marked with a double line ...
I will plan a 50 Mwp project by conducting feasibility studies, creating a detailed project timeline, securing necessary permits, sourcing materials and contractors, and implementing a quality control plan.
Conduct feasibility studies to assess site suitability and potential challenges
Create a detailed project timeline outlining key milestones and deadlines
Secure necessary permits and approvals from local authorities
Sou...
MSP (Microsoft Project) is a project management software developed by Microsoft, while Primavera is a project management software developed by Oracle.
MSP is developed by Microsoft, while Primavera is developed by Oracle.
MSP is more commonly used for smaller projects, while Primavera is preferred for larger and more complex projects.
MSP is known for its user-friendly interface and ease of use, while Primavera is known f...
I applied via Recruitment Consulltant and was interviewed in Jun 2023. There were 4 interview rounds.
posted on 6 Sep 2023
posted on 10 Nov 2023
I applied via Approached by Company and was interviewed in Oct 2023. There were 3 interview rounds.
posted on 2 Feb 2024
I applied via Approached by Company and was interviewed in Aug 2023. There were 3 interview rounds.
posted on 18 Apr 2022
I applied via Walk-in and was interviewed before Apr 2021. There were 2 interview rounds.
A step-up transformer is used to increase the voltage in an electrical circuit.
Step-up transformers have more turns in the secondary coil than in the primary coil.
They work based on the principle of electromagnetic induction.
The primary coil is connected to a power source with a lower voltage, while the secondary coil is connected to the load.
The increased voltage in the secondary coil is proportional to the ratio of t...
The commissioning process of a PV solar plant involves testing, adjusting, and optimizing the system to ensure it is functioning properly.
Testing the electrical components and connections to ensure they are working correctly
Adjusting the system settings to maximize efficiency and output
Optimizing the performance of the solar panels to achieve the desired energy production
Checking for any potential issues or malfunction
Transformer types of testing include routine tests, type tests, and special tests to ensure proper functioning and safety.
Routine tests include insulation resistance, turns ratio, and polarity tests.
Type tests are conducted on a prototype to verify design parameters like temperature rise and short-circuit withstand.
Special tests may include impulse voltage, partial discharge, and noise level tests.
Testing ensures trans...
based on 2 reviews
Rating in categories
Assistant Engineer
40
salaries
| ₹1.8 L/yr - ₹4.3 L/yr |
Engineer
24
salaries
| ₹2.8 L/yr - ₹5.5 L/yr |
Electrical Engineer
22
salaries
| ₹2.5 L/yr - ₹6 L/yr |
Assistant Manager
17
salaries
| ₹6 L/yr - ₹10.4 L/yr |
Senior Engineer
17
salaries
| ₹4.5 L/yr - ₹6.4 L/yr |
Dhoot Transmission
R.K.M Powergen
SHV Energy
New Allenberry Works