Wind calculation as per IS875 involves determining wind loads on structures based on specified parameters.
IS875 provides guidelines for calculating wind loads on structures in India
Factors such as wind speed, terrain category, and building height are considered
Wind loads are calculated using formulas provided in the code
Example: Wind load calculation for a tall building in a coastal area would be different from a build
Base shear calculation as per IS1893 involves determining the seismic force acting on a structure.
Base shear is calculated using the formula V = AhW, where V is the base shear, A is the seismic coefficient, h is the height of the structure, and W is the total seismic weight of the structure.
Seismic coefficient A is determined based on the seismic zone and the importance factor of the structure as per IS1893.
The total s...
3D STAAD design and analysis.
I applied via Referral and was interviewed before Apr 2023. There was 1 interview round.
I applied via Naukri.com and was interviewed before Mar 2023. There was 1 interview round.
Planning for production involves creating a detailed schedule, coordinating resources, and optimizing efficiency.
Develop a production schedule to ensure timely delivery of products
Coordinate with different departments to allocate resources effectively
Optimize production processes to increase efficiency and reduce costs
I applied via Referral and was interviewed in Oct 2022. There were 2 interview rounds.
I applied via Referral and was interviewed in Nov 2021. There were 2 interview rounds.
I was interviewed before Jan 2021.
Diploma
I applied via Approached by Company and was interviewed before Dec 2023. There were 2 interview rounds.
A treatment plant is a facility where wastewater is treated to remove contaminants before being discharged back into the environment.
Treatment plants use a combination of physical, chemical, and biological processes to remove pollutants from wastewater.
Common processes in treatment plants include screening, sedimentation, filtration, and disinfection.
Examples of treatment plants include sewage treatment plants, water t...
Bus bar schemes are different ways of connecting bus bars in power systems.
Single bus bar scheme
Double bus bar scheme
Main and transfer bus bar scheme
Ring bus bar scheme
Breaker and a half scheme
Mesh bus bar scheme
The equipment sequence for any line bay starts with the circuit breaker and ends with the transformer.
The circuit breaker is the first equipment in the sequence.
Next comes the isolator switch.
After that, the earth switch is operated.
Then the line disconnector is opened.
Finally, the transformer is disconnected from the line.
The sequence is reversed when the line bay is put back into service.
based on 1 interview
Interview experience
based on 6 reviews
Rating in categories
Assistant Manager
76
salaries
| ₹0 L/yr - ₹0 L/yr |
Design Engineer
46
salaries
| ₹0 L/yr - ₹0 L/yr |
Senior Engineer
45
salaries
| ₹0 L/yr - ₹0 L/yr |
Production Engineer
41
salaries
| ₹0 L/yr - ₹0 L/yr |
Safety Officer
41
salaries
| ₹0 L/yr - ₹0 L/yr |
Tata BlueScope Steel
Jindal Steel and Power
Everest Industries
Pennar Industries