Minimum tests for piling include integrity testing, load testing, and pile driving analyzer (PDA) testing.
Integrity testing is done to ensure that the pile is free from defects and damage.
Load testing is done to determine the load capacity of the pile.
Pile driving analyzer (PDA) testing is done to measure the stresses and strains in the pile during driving.
Other tests may include crosshole sonic logging (CSL) and therm
Top trending discussions
I applied via Walk-in and was interviewed in Aug 2023. There were 3 interview rounds.
I applied via Recruitment Consulltant and was interviewed before Jan 2023. There was 1 interview round.
I applied via Walk-in and was interviewed in Oct 2021. There was 1 interview round.
I applied via Company Website and was interviewed in Apr 2021. There was 1 interview round.
I applied via Recruitment Consultant and was interviewed in Dec 2020. There were 3 interview rounds.
based on 1 interview
Interview experience
based on 1 review
Rating in categories
Senior Engineer
36
salaries
| ₹4.2 L/yr - ₹9.2 L/yr |
Assistant Manager
29
salaries
| ₹4.4 L/yr - ₹11 L/yr |
Project Engineer
14
salaries
| ₹3 L/yr - ₹7 L/yr |
Senior Project Engineer
11
salaries
| ₹4 L/yr - ₹6.1 L/yr |
Safety Officer
11
salaries
| ₹3.8 L/yr - ₹5.5 L/yr |
Thermax Limited
Suzlon Group
Larsen & Toubro Limited
BHEL