Q1. what is CPI, BCWP , ETc
Ans.
CPI stands for Cost Performance Index, BCWP stands for Budgeted Cost of Work Performed, and ETC stands for Estimate to Complete.
CPI is a measure of cost efficiency on a project, calculated as BCWP divided by ACWP (Actual Cost of Work Performed). A CPI greater than 1 indicates cost efficiency.
BCWP represents the budgeted cost of work that has been completed up to a specific point in time.
ETC is an estimate of the cost required to complete the remaining work on a project.
These ...read more
Are these interview questions helpful?
Interview Questions of Similar Designations
Senior Engineer Interview Questions and Answers
1.9k Questions
Project Engineer Interview Questions and Answers
1.1k Questions
Junior Engineer Interview Questions and Answers
1k Questions
Civil Site Engineer Interview Questions and Answers
902 Questions
Site Engineer Interview Questions and Answers
823 Questions
Interview Tips & Stories
Ace your next interview with expert advice and inspiring stories
Calculate your in-hand salary
Confused about how your in-hand salary is calculated? Enter your annual salary (CTC) and get your in-hand salary
Share an Interview
Stay ahead in your career. Get AmbitionBox app
Helping over 1 Crore job seekers every month in choosing their right fit company
65 L+
Reviews
4 L+
Interviews
4 Cr+
Salaries
1 Cr+
Users/Month
Contribute to help millions
Get AmbitionBox app