Why do we take only 1 set of cube sample at a casting of concrete of 5 or less than 5 Meter cube.
AnswerBot
1y
Only 1 set of cube sample is taken at a casting of concrete of 5 or less than 5 Meter cube to save cost and time.
Taking multiple samples would increase the cost of testing.
The strength of concrete is ...read more
RAMBARAN SINGH BHADORIYA
3mo
1 SET OF 3 NOS CUBE AS PER IS 516 SPECIFICATION
Siddhi Joshi
1y
Kyo ki hum four test karte hai 3 day, 7day,14day,28 day .......
Md Rashid
1y
After 6 cubic meter concrete is poured, there is a need for cub testing.
Anonymous
1y
1set by 3cube and 5m3 concrete cube casting for minimum 6 cube
Anonymous
1y
Kyo ki ham four test karte hai 3day,7day,14day,28day
Anonymous
2y
No, minimum 6cum one set cube
Hafeez Shaik
2y
As per IS 456:2000, minimum samples of cube per m^3 concrete is for 1-5m^3 of concrete 1 sample is 3 cubes
Hafeez Shaik
2y
As per IS 456:2000, minimum samples of cube per m^3 concrete is for 1-5m^3 of concrete 1 sample is 3 cubes
Add answer anonymously...
Top Nagarjuna Construction Company Assistant Engineer interview questions & answers
Popular interview questions of Assistant Engineer
Top HR questions asked in Nagarjuna Construction Company Assistant Engineer
>
Nagarjuna Construction Company Assistant Engineer Interview Questions
Stay ahead in your career. Get AmbitionBox app
Helping over 1 Crore job seekers every month in choosing their right fit company
65 L+
Reviews
4 L+
Interviews
4 Cr+
Salaries
1 Cr+
Users/Month
Contribute to help millions
Get AmbitionBox app