What is the procedure to start the earthen dam
AnswerBot
1y
The procedure to start an earthen dam involves site selection, design, construction, and maintenance.
Site selection involves identifying a suitable location with adequate soil and water resources.
Desi...read more
S K
1y
There are two methods of constructing earthen dams: (1) Hydraulic-fill Method; and (2) Rolled-fill Method. (2) Rolled-fill Method. (1) Hydraulic-fill Method. In this method of construction, the dam bo...read more
Anonymous
3y
First cleaning, level taken & stripping again level taken then cot excavation. Etc
Add answer anonymously...
Top Megha Engineering & Infrastructures Civil Engineer interview questions & answers
Popular interview questions of Civil Engineer
Top HR questions asked in Megha Engineering & Infrastructures Civil Engineer
>
Megha Engineering & Infrastructures Civil Engineer Interview Questions
Stay ahead in your career. Get AmbitionBox app
Helping over 1 Crore job seekers every month in choosing their right fit company
65 L+
Reviews
4 L+
Interviews
4 Cr+
Salaries
1 Cr+
Users/Month
Contribute to help millions
Get AmbitionBox app