Mahaveer Group
Netrika Consulting Interview Questions and Answers
Q1. What is the mix ratio of m20 grade of concrete
The mix ratio of M20 grade of concrete is 1:1.5:3.
The mix ratio of M20 grade of concrete means the proportion of cement, sand, and aggregate used in the concrete mix.
For M20 grade concrete, the mix ratio is 1 part cement : 1.5 parts sand : 3 parts aggregate.
This means that for every 1 part of cement, 1.5 parts of sand, and 3 parts of aggregate are used.
For example, if you have 1 bag of cement (50 kg), you would need 1.5 bags of sand (75 kg) and 3 bags of aggregate (150 kg) to...read more
Q2. What is the unit weight of steel
The unit weight of steel varies depending on its type and grade.
The unit weight of steel is typically measured in pounds per cubic foot (lb/ft³) or kilograms per cubic meter (kg/m³).
The unit weight of common structural steel ranges from 490 to 7850 pounds per cubic foot (7850 to 12600 kg/m³).
For example, the unit weight of mild steel is approximately 490 pounds per cubic foot (7850 kg/m³).
Q3. What is the clear cover for beam
The clear cover for a beam is the distance between the outer surface of the beam and the nearest surface of the concrete cover.
Clear cover is important to protect the reinforcement from corrosion and fire.
The clear cover for beams is typically specified in construction drawings or codes.
The clear cover can vary depending on the type of beam and its exposure conditions.
For example, in a residential building, the clear cover for a beam may be around 25-30 mm.
In a marine environ...read more
Q4. What is the height of parapet wall
The height of a parapet wall varies depending on its purpose and location.
The height of a parapet wall is typically determined by building codes and regulations.
In residential buildings, parapet walls are usually around 3 feet tall to provide safety and privacy.
In commercial or industrial buildings, parapet walls can be higher to serve as a barrier against noise, wind, or to hide rooftop equipment.
Historical buildings may have taller parapet walls for architectural purposes.
T...read more
Q5. What is the LD for column
LD for column refers to Liquidated Damages for delay in completing the column construction.
LD stands for Liquidated Damages.
It is a predetermined amount of money that the contractor will pay to the client in case of delay in completing the project.
LD for column specifically refers to the amount of money that will be deducted for each day of delay in constructing the column.
The LD amount is usually mentioned in the contract agreement between the client and the contractor.
It is...read more
Q6. How do u manage vendors
Managing vendors involves communication, negotiation, and relationship building.
Establish clear expectations and requirements
Communicate regularly to ensure alignment
Negotiate terms and pricing to achieve mutual benefit
Build strong relationships based on trust and respect
Monitor performance and provide feedback for improvement
Resolve conflicts promptly and professionally
Q7. Steps to do bill checking
Bill checking involves verifying quantities, rates, and calculations in a construction project invoice.
Review the bill for accuracy in quantities, rates, and calculations
Check for any discrepancies or errors in the bill
Verify that all items listed in the bill match the actual work done
Ensure that the bill includes all necessary documentation and supporting details
Cross-check the bill with the contract agreement and any change orders
Seek clarification from the contractor or su...read more
Top Interview Questions from Similar Companies
Reviews
Interviews
Salaries
Users/Month