Kamal Coach Works Interview Questions and Answers

Updated 5 Feb 2024

Q1. What are the tests to be conducted before charging of Power transformer.

Ans.

Tests to be conducted before charging of Power transformer

  • Insulation resistance test

  • Polarity and phase-relation test

  • Turns ratio test

  • Vector group test

  • Oil test

  • Functional test

Add your answer

Q2. How to get the exact eath values, even in Rocky areas where size kf pit and earthing pipe remains same.

Ans.

Use advanced earthing techniques and equipment to accurately measure earth values in rocky areas.

  • Use specialized equipment like clamp-on ground resistance testers

  • Install additional grounding rods to improve accuracy

  • Consider using chemical electrodes for better contact with the ground

  • Ensure proper installation and maintenance of earthing system

  • Consult with experts in earthing and grounding for best practices

Add your answer

Q3. how to control theft and minimise the material wastage in RE projects

Ans.

Implement strict inventory management, conduct regular audits, and train employees on theft prevention and material handling.

  • Implement a strict inventory management system to keep track of all materials and equipment.

  • Conduct regular audits to identify any discrepancies or missing items.

  • Train employees on theft prevention techniques and proper material handling procedures.

  • Install security cameras and alarms to deter theft.

  • Use tamper-proof locks and secure storage areas for hig...read more

Add your answer

Q4. What is the charging current of transmission line in OH conditions and in UG conditions.

Ans.

Charging current of transmission line varies based on the conditions - OH or UG.

  • Charging current is the current that flows through the capacitance of the transmission line.

  • In OH conditions, the charging current is higher due to the larger distance between the conductors and the ground.

  • In UG conditions, the charging current is lower due to the smaller distance between the conductors and the ground.

  • The charging current also depends on the voltage level and the length of the tra...read more

Add your answer
Discover Kamal Coach Works interview dos and don'ts from real experiences

Q5. What are the scheduled maintenance program of a TSS, PSS.

Ans.

Scheduled maintenance programs for TSS and PSS

  • TSS (Total Suspended Solids) requires regular cleaning of filters and monitoring of chemical levels

  • PSS (Particulate Suspended Solids) requires regular cleaning of filters and monitoring of pressure levels

  • Both TSS and PSS require regular calibration of instruments and replacement of worn out parts

  • Maintenance schedules may vary depending on the specific equipment and usage

  • Regular maintenance helps ensure optimal performance and prol...read more

Add your answer

Q6. Standard of railway crossings kf 33/11/132/440 kV lines as per RDSO

Ans.

The standard of railway crossings for different voltage lines as per RDSO.

  • RDSO specifies different standards for railway crossings based on the voltage of the lines.

  • For 33 kV lines, the minimum height of the overhead equipment is 5.5 meters.

  • For 11 kV lines, the minimum height of the overhead equipment is 5 meters.

  • For 132 kV lines, the minimum height of the overhead equipment is 7 meters.

  • For 440 kV lines, the minimum height of the overhead equipment is 9 meters.

  • The standards a...read more

Add your answer

Q7. what is differential potential of transformer.

Ans.

Differential potential of transformer is the voltage difference between the primary and secondary windings.

  • It is a measure of the transformer's ability to isolate the primary and secondary circuits.

  • It is important for safety and proper functioning of the transformer.

  • The differential potential is affected by the turns ratio and the insulation between the windings.

  • A high differential potential can cause arcing and damage to the transformer.

  • Proper maintenance and testing can ens...read more

Add your answer

Q8. SOP of RE projects.

Ans.

SOP of RE projects involves defining project scope, identifying stakeholders, creating project plan, executing and monitoring progress.

  • Define project scope and objectives

  • Identify stakeholders and their requirements

  • Create project plan with timelines and milestones

  • Execute project plan and monitor progress

  • Manage risks and issues

  • Ensure quality control and compliance

  • Close out project and conduct lessons learned

Add your answer
Contribute & help others!
Write a review
Share interview
Contribute salary
Add office photos

Interview Process at Kamal Coach Works

based on 1 interviews
Interview experience
3.0
Average
View more
Interview Tips & Stories
Ace your next interview with expert advice and inspiring stories

Top Manager Interview Questions from Similar Companies

3.7
 • 37 Interview Questions
3.9
 • 24 Interview Questions
3.4
 • 15 Interview Questions
3.8
 • 14 Interview Questions
4.0
 • 13 Interview Questions
4.1
 • 12 Interview Questions
View all
Share an Interview
Stay ahead in your career. Get AmbitionBox app
qr-code
Helping over 1 Crore job seekers every month in choosing their right fit company
70 Lakh+

Reviews

5 Lakh+

Interviews

4 Crore+

Salaries

1 Cr+

Users/Month

Contribute to help millions

Made with ❤️ in India. Trademarks belong to their respective owners. All rights reserved © 2024 Info Edge (India) Ltd.

Follow us
  • Youtube
  • Instagram
  • LinkedIn
  • Facebook
  • Twitter