Q1. What is inspected you before during and after welding ?
Before, during, and after welding, various aspects are inspected to ensure quality and safety.
Before welding, the materials and equipment are inspected for cleanliness, proper setup, and suitability for the welding process.
During welding, the inspector checks for proper welding technique, adherence to welding procedures, and the quality of welds being produced.
After welding, the inspector inspects the completed welds for defects such as cracks, porosity, incomplete fusion, an...read more
Q2. How to inspected and released fabrication spool before send to erection site
Fabrication spools must be inspected thoroughly before releasing to the erection site.
Check for any defects or damages on the spool.
Ensure that the spool meets the required specifications and standards.
Verify that all necessary documentation and certifications are in place.
Perform visual and dimensional inspections on the spool.
Conduct hydrostatic testing to check for leaks or other issues.
Ensure that the spool is properly labeled and identified.
Coordinate with other departme...read more
Q3. What you will in check RT films ? What is sensitivity calculation
In RT film check, I will inspect for any defects or anomalies in the radiographic image. Sensitivity calculation is the measure of the smallest detectable flaw.
Inspect for any defects or anomalies in the radiographic image
Check for proper exposure and contrast
Ensure that the film is free from any artifacts or processing errors
Calculate the sensitivity of the film to detect the smallest flaw
Use a penetrameter to determine the sensitivity of the film
Compare the penetrameter ima...read more
Q4. What u will be check on time Ground Inspection or IMIR
I will check both Ground Inspection and IMIR for quality control purposes.
I will check the ground inspection report for any discrepancies or issues with the physical product.
I will also review the IMIR (In-Process Material Inspection Report) to ensure that all necessary inspections and tests have been completed.
I will verify that all required documentation is present and accurate.
I will communicate any issues or concerns to the appropriate parties for resolution.
Examples of i...read more
Q5. What u will check at during spool erection time
During spool erection time, I will check for proper alignment, fit-up, welding quality, and dimensional accuracy.
Check for proper alignment of spool components
Ensure fit-up is correct and there are no gaps or misalignments
Inspect welding quality for defects such as cracks, porosity, and incomplete fusion
Verify dimensional accuracy of the spool according to the design specifications
Check for any damage or corrosion on the spool components
Q6. What is hydro test procedures?
Hydro test procedures involve filling a vessel or pipeline with water and pressurizing it to check for leaks or structural integrity.
The vessel or pipeline is filled with water
The water is pressurized to a predetermined level
The pressure is held for a specified amount of time
The vessel or pipeline is inspected for leaks or structural damage
If no issues are found, the water is drained and the vessel or pipeline is deemed safe for use
Examples include testing the integrity of a ...read more