Q1. Before hydrotest what requirements?
Before hydrotest, the requirements include completion of piping installation, flushing, cleaning, and pressure testing.
Completion of piping installation to ensure all components are in place
Flushing to remove any debris or contaminants from the piping system
Cleaning to ensure the piping system is free from any foreign materials
Pressure testing to verify the integrity of the piping system under operating conditions
Q2. Differ between pipe and tube?
Pipe is measured by its inner diameter, while tube is measured by its outer diameter.
Pipe is used to transport fluids or gases, while tube is often used for structural purposes.
Pipe is typically manufactured to specific industry standards, while tube may have more variation in size and thickness.
Examples: PVC pipe for plumbing, steel tube for construction.
Q3. Who is responsible for a lifting plan
The lifting plan is typically the responsibility of the rigging engineer or supervisor.
The rigging engineer or supervisor is responsible for creating and implementing a lifting plan.
They assess the load, determine the appropriate rigging equipment and techniques, and ensure compliance with safety regulations.
The lifting plan may also involve coordination with other departments or personnel, such as crane operators or project managers.
Examples of lifting plans include plans fo...read more
Q4. What is critical lifting
Critical lifting refers to the process of lifting heavy or delicate loads that require careful planning and execution to ensure safety and prevent damage.
Critical lifting involves lifting loads that are heavy or delicate and require special attention.
It requires careful planning and coordination to ensure the safety of personnel and equipment.
Factors such as load weight, center of gravity, lifting equipment, and environmental conditions must be considered.
Examples of critical...read more
Q5. How you will reach zero goal on time completion of work on daily basis explain.
Q6. Experience on oil and gas construction
I have extensive experience in oil and gas construction.
Managed construction projects for oil and gas pipelines
Coordinated with contractors and subcontractors to ensure project completion on time and within budget
Implemented safety protocols to ensure compliance with industry regulations
Experience with welding, piping, and instrumentation
Familiarity with industry standards and codes such as ASME, API, and ANSI
Q7. Technical experience on Oil and Gas
I have extensive technical experience in the Oil and Gas industry.
I have worked on various projects related to drilling, production, and refining.
I am familiar with industry standards and regulations such as API and ASME codes.
I have experience in designing and implementing safety measures to prevent accidents and ensure compliance.
I have worked with various equipment and technologies such as pumps, compressors, and pipelines.
I have also managed projects from conception to co...read more