Q1. What is earned value analysis?
Earned value analysis is a project management technique to measure project performance and progress.
Earned value analysis compares the planned value, earned value, and actual cost of a project.
Planned value (PV) is the budgeted cost of the work scheduled to be completed.
Earned value (EV) is the budgeted cost of the work actually completed.
Actual cost (AC) is the actual cost incurred for the work completed.
By comparing PV, EV, and AC, earned value analysis helps in assessing p...read more
Q2. How to crash a schedule?
Crashing a schedule involves reducing the project duration by adding additional resources or increasing their efficiency.
Identify critical path activities
Determine the activities that can be crashed
Add additional resources to those activities
Increase the efficiency of resources
Re-evaluate the schedule to ensure feasibility
Q3. What is critical path method?
Critical Path Method is a project management technique used to determine the longest sequence of activities in a project.
Critical Path Method helps in identifying the activities that are critical to the project's timeline.
It involves creating a network diagram to visualize the project's activities and their dependencies.
The critical path is the longest path in the network diagram and determines the project's overall duration.
Activities on the critical path must be closely mon...read more
Q4. Procedure for preparing a schedule?
The procedure for preparing a schedule involves several steps.
Identify project tasks and activities
Determine the sequence and dependencies of tasks
Estimate the duration of each task
Allocate resources to tasks
Create a project timeline
Review and adjust the schedule as needed