Crest is the highest point of a layer in a pavement structure.
Crest is also known as the high point.
It is important to ensure that the crest is properly designed and constructed to prevent water from pooling on the surface.
The thickness of the layer at the crest should be sufficient to support the traffic loads.
Examples of layers in a pavement structure include the subgrade, base course, and surface course.
Tolerance of top layers in highway engineering
Tolerance refers to the acceptable deviation from the design specifications
Top layers of a highway include asphalt, concrete, or other materials
Tolerance is important to ensure the safety and durability of the road
Factors affecting tolerance include climate, traffic volume, and materials used
Regular maintenance and inspections can help identify and address tolerance issues
Top trending discussions
I applied via Naukri.com and was interviewed before Mar 2021. There were 4 interview rounds.
Technical questions related to domain.
Carbonation is the process of dissolving carbon dioxide gas in a liquid.
Occurs naturally in carbonated mineral water
Used in the production of carbonated beverages
Can affect the pH of a liquid
Can cause corrosion in concrete structures
Pratical test by Auto level.
I applied via Campus Placement and was interviewed before Jul 2020. There were 2 interview rounds.
I applied via Naukri.com and was interviewed in May 2019. There were 3 interview rounds.
My current position involves leading cross-functional teams and driving technical innovation.
I am responsible for leading a team of engineers in developing new products and technologies.
I work closely with other departments such as marketing and sales to ensure alignment on project goals.
I am involved in setting technical direction and strategy for the team, as well as mentoring junior engineers.
I have successfully imp...
I applied via Company Website and was interviewed in May 2019. There were 4 interview rounds.
I appeared for an interview in Jul 2020.
I applied via Campus Placement and was interviewed before May 2022. There were 3 interview rounds.
Test based on basic Mining knowledge
I applied via Indeed and was interviewed in Jul 2023. There were 2 interview rounds.
The erection of a cement mill involves the installation and assembly of the mill equipment and machinery.
The cement mill is typically a large cylindrical structure where raw materials are ground into fine powder.
The erection process includes the installation of the mill shell, liners, diaphragm, and grinding media.
Proper alignment and leveling of the mill components are crucial for efficient operation.
Electrical and me...
The procedure of erection involves the process of assembling and installing structural components to create a stable and functional structure.
Planning and preparation
Site preparation and foundation
Assembly of structural components
Installation of utilities and systems
Finishing and testing
Final inspection and handover
Planning of the erection involves creating a detailed plan for the construction process.
Identify the scope and objectives of the project
Determine the sequence of activities and their dependencies
Allocate resources and manpower
Create a schedule and timeline
Consider safety measures and risk management
Coordinate with other teams and stakeholders
Monitor progress and make adjustments as necessary
I applied via Recruitment Consultant and was interviewed before Aug 2022. There were 2 interview rounds.
Assistant Manager
159
salaries
| ₹3.6 L/yr - ₹12.5 L/yr |
Officer
47
salaries
| ₹2.8 L/yr - ₹7 L/yr |
Manager
43
salaries
| ₹7 L/yr - ₹21.5 L/yr |
Engineer
43
salaries
| ₹2.4 L/yr - ₹7.8 L/yr |
Assistant General Manager
37
salaries
| ₹11 L/yr - ₹30 L/yr |
UltraTech Cement
JK Cement
Grasim Industries
ACC