Q1. What is Total Flot and Free Floatof a Project ?

Ans.

Total Float and Free Float are two important concepts in project management that help in scheduling and resource allocation.

  • Total Float is the amount of time a task can be delayed without affecting the project deadline.

  • Free Float is the amount of time a task can be delayed without affecting the start time of the next task.

  • Total Float = Late Finish - Early Finish or Late Start - Early Start

  • Free Float = Early Start of Next Task - Late Finish of Current Task

  • Both Total Float and ...read more

Add your answer

Q2. What is contains in the First Row of a Billing ?

Ans.

The first row of a billing typically contains the name and address of the client or customer.

  • Name and address of the client

  • Date of the billing

  • Invoice number

  • Description of the work done

  • Quantity of work done

  • Rate per unit

  • Total amount

Add your answer

Q3. From where you can find rate of a quantity ?

Ans.

Rate of a quantity can be found from various sources.

  • Check government websites for official rates

  • Consult with industry experts

  • Research market trends and prices

  • Refer to pricing indexes and databases

Add your answer

Q4. How to use Array command in Auto Cad?

Ans.

Array command in AutoCAD is used to create multiple copies of objects in a pattern.

  • Select the object to be copied

  • Specify the base point for the array

  • Specify the distance and direction of the array

  • Specify the number of rows and columns in the array

  • Choose between rectangular and polar array

  • Press enter to complete the array

Add your answer
Discover Ipshopy interview dos and don'ts from real experiences

Q5. How to approved a contractor's bill ?

Ans.

A contractor's bill can be approved by verifying the work done and comparing it with the contract terms and conditions.

  • Verify the work done by the contractor

  • Compare the work done with the contract terms and conditions

  • Check for any discrepancies or errors in the bill

  • Ensure that all necessary documents and approvals are in place

  • Approve the bill only after thorough verification

Add your answer

Q6. What is Critical Path of a Project ?

Ans.

Critical Path is the longest sequence of activities in a project that must be completed on time to ensure the project is completed on schedule.

  • Critical Path determines the minimum time required to complete a project.

  • It helps in identifying the activities that are critical to the project's success.

  • Any delay in the critical path activities will delay the project's completion.

  • It involves identifying all the activities, their dependencies, and their duration.

  • Examples of critical ...read more

Add your answer

Q7. Is critical path deviates ?

Ans.

No, critical path cannot deviate.

  • Critical path is the longest path in a project network diagram.

  • It determines the shortest possible duration of the project.

  • Any deviation from the critical path will result in a delay in the project completion.

  • Therefore, the critical path cannot deviate.

Add your answer
Contribute & help others!
Write a review
Share interview
Contribute salary
Add office photos
Interview Tips & Stories
Ace your next interview with expert advice and inspiring stories
Share an Interview
Stay ahead in your career. Get AmbitionBox app
qr-code
Helping over 1 Crore job seekers every month in choosing their right fit company
70 Lakh+

Reviews

5 Lakh+

Interviews

4 Crore+

Salaries

1 Cr+

Users/Month

Contribute to help millions

Made with ❤️ in India. Trademarks belong to their respective owners. All rights reserved © 2024 Info Edge (India) Ltd.

Follow us
  • Youtube
  • Instagram
  • LinkedIn
  • Facebook
  • Twitter