Q1. What is Total Flot and Free Floatof a Project ?
Total Float and Free Float are two important concepts in project management that help in scheduling and resource allocation.
Total Float is the amount of time a task can be delayed without affecting the project deadline.
Free Float is the amount of time a task can be delayed without affecting the start time of the next task.
Total Float = Late Finish - Early Finish or Late Start - Early Start
Free Float = Early Start of Next Task - Late Finish of Current Task
Both Total Float and ...read more
Q2. What is contains in the First Row of a Billing ?
The first row of a billing typically contains the name and address of the client or customer.
Name and address of the client
Date of the billing
Invoice number
Description of the work done
Quantity of work done
Rate per unit
Total amount
Q3. From where you can find rate of a quantity ?
Rate of a quantity can be found from various sources.
Check government websites for official rates
Consult with industry experts
Research market trends and prices
Refer to pricing indexes and databases
Q4. How to use Array command in Auto Cad?
Array command in AutoCAD is used to create multiple copies of objects in a pattern.
Select the object to be copied
Specify the base point for the array
Specify the distance and direction of the array
Specify the number of rows and columns in the array
Choose between rectangular and polar array
Press enter to complete the array
Q5. How to approved a contractor's bill ?
A contractor's bill can be approved by verifying the work done and comparing it with the contract terms and conditions.
Verify the work done by the contractor
Compare the work done with the contract terms and conditions
Check for any discrepancies or errors in the bill
Ensure that all necessary documents and approvals are in place
Approve the bill only after thorough verification
Q6. What is Critical Path of a Project ?
Critical Path is the longest sequence of activities in a project that must be completed on time to ensure the project is completed on schedule.
Critical Path determines the minimum time required to complete a project.
It helps in identifying the activities that are critical to the project's success.
Any delay in the critical path activities will delay the project's completion.
It involves identifying all the activities, their dependencies, and their duration.
Examples of critical ...read more
Q7. Is critical path deviates ?
No, critical path cannot deviate.
Critical path is the longest path in a project network diagram.
It determines the shortest possible duration of the project.
Any deviation from the critical path will result in a delay in the project completion.
Therefore, the critical path cannot deviate.