Boiler light up procedure .
AnswerBot
1y
The boiler light up procedure is the process of starting and igniting a boiler to generate steam.
Ensure all safety measures are in place before starting the procedure.
Open the boiler's fuel and air su...read more
GOKUL DADAJI WASADE
2y
Cold light up
First steam drum fill 60 %
Charcoal take in furnace
ID Fan on for natural draft maintain
Charcoal fire upto 600 °C
In 2 compartment, 1st compartment lightup then other.
Mixing properly
2nd co...read more
Suraj Raut
4y
Boiler light up procedure is a process during the maintainance time or shutdown time the remove the watrer and condensate from boiller by using CEP pump.
Anuj K. Pandey
4y
CEP Pump start,
Add answer anonymously...
Top Thermax Limited Control Room Engineer interview questions & answers
Top HR questions asked in Thermax Limited Control Room Engineer
>
Thermax Limited Control Room Engineer Interview Questions
Stay ahead in your career. Get AmbitionBox app
Helping over 1 Crore job seekers every month in choosing their right fit company
65 L+
Reviews
4 L+
Interviews
4 Cr+
Salaries
1 Cr+
Users/Month
Contribute to help millions
Get AmbitionBox app