Q1. What is Contract Agreement? What is FIDIC Contract? What is EPC Contract?

Add your answer

Q2. Are you familiar with Specifications? What is BIS, ASTM, BS and Good Industrial Practice?

Add your answer

Q3. Do you have any idea about Static Load Test and Dynamic Load Test?

Add your answer

Q4. Do you know PPP Project? What do you mean by Concessionaire and Grantor?

Add your answer
Discover ALPNA ENTERPRISES interview dos and don'ts from real experiences

Q5. What do you understand by project review and monitoring?

Add your answer

Q6. What is the importance of HSE in an infrastructure project?

Add your answer
Are these interview questions helpful?

Q7. What is lt pole election rull

Ans.

LT pole election rule refers to the guidelines and regulations for selecting and installing low tension electrical poles.

  • LT pole election rule specifies the criteria for selecting the appropriate location for installing low tension electrical poles.

  • It includes factors such as distance from buildings, roadways, and other structures, as well as soil conditions and accessibility.

  • Compliance with LT pole election rule ensures safe and efficient distribution of electricity.

  • For exam...read more

View 1 answer

Q8. What type of structures you worked?

Add your answer
Share interview questions and help millions of jobseekers 🌟

Q9. What is ptr full name

Ans.

PTR stands for Project Technical Report.

  • PTR is a document that summarizes the technical aspects of a project.

  • It includes details such as project scope, objectives, methodology, results, and conclusions.

  • PTRs are often used to communicate project progress and findings to stakeholders.

View 1 answer

Q10. Are you acquainted with elevated expressway?

Add your answer

Q11. What is Resource Based Realistic Work Program?

Add your answer

Q12. Do you have experience of Highway Works?

Add your answer

Q13. Do You know about a Environmental Management Plan?

Add your answer

Q14. What is Bentonite and why it is used in structure?

Add your answer

Q15. Five fit depth with coil earthing

Ans.

Coil earthing is a method of grounding electrical systems to prevent electric shock and ensure safety.

  • Coil earthing involves burying a coil of wire in the ground to create a low-resistance path for electrical currents to flow safely.

  • The depth at which the coil should be buried depends on factors such as soil type, moisture content, and local regulations.

  • Proper installation of coil earthing is essential to protect equipment and personnel from electrical hazards.

  • Regular mainten...read more

Add your answer

Q16. Do you have knowledge of QA/QC?

Add your answer

Q17. Do you know to review Shop Drawings?

Add your answer

Q18. Dtr & PSS structure of SLD.

Ans.

Dtr & PSS structure of SLD refers to Distribution Transformer and Package Substation structure in Single Line Diagram.

  • Dtr stands for Distribution Transformer which is used to step down voltage for distribution purposes.

  • PSS stands for Package Substation which is a compact unit containing transformers, switchgear, and control equipment.

  • In a Single Line Diagram (SLD), Dtr and PSS are represented by symbols to show their location and connections.

  • The Dtr symbol typically includes ...read more

Add your answer

Q19. What do you mean by Curing?

Add your answer

Q20. What are types of Contract and Claims

Ans.

Types of contracts include fixed-price, cost-reimbursable, and time and material. Claims can be for delay, disruption, or breach of contract.

  • Fixed-price contracts involve a set price for the project, regardless of actual costs.

  • Cost-reimbursable contracts involve the contractor being reimbursed for actual costs incurred, plus a fee.

  • Time and material contracts involve paying for the contractor's time and materials used.

  • Claims for delay can be made when the project takes longer ...read more

Add your answer

Q21. Process of variation

Ans.

Process of variation involves documenting and analyzing changes in project scope, cost, or schedule.

  • Variations are changes to the original scope, cost, or schedule of a project

  • Variations must be documented and approved by the relevant parties

  • The impact of variations on project budget and timeline must be analyzed

  • Examples of variations include design changes, unforeseen site conditions, and client requests

Add your answer

Q22. What is Contract

Ans.

A legally binding agreement between two or more parties that outlines the terms and conditions of a transaction or relationship.

  • Contract is a written or verbal agreement between parties

  • It outlines the terms and conditions of a transaction or relationship

  • It is legally binding and enforceable by law

  • Examples include employment contracts, rental agreements, and construction contracts

Add your answer
Contribute & help others!
Write a review
Share interview
Contribute salary
Add office photos

Interview Process at ALPNA ENTERPRISES

based on 12 interviews
Interview experience
4.4
Good
View more
Interview Tips & Stories
Ace your next interview with expert advice and inspiring stories

Top Interview Questions from Similar Companies

3.9
 • 782 Interview Questions
3.9
 • 517 Interview Questions
3.8
 • 181 Interview Questions
3.9
 • 179 Interview Questions
3.9
 • 145 Interview Questions
View all
Top The Louis Berger Group Interview Questions And Answers
Share an Interview
Stay ahead in your career. Get AmbitionBox app
qr-code
Helping over 1 Crore job seekers every month in choosing their right fit company
75 Lakh+

Reviews

5 Lakh+

Interviews

4 Crore+

Salaries

1 Cr+

Users/Month

Contribute to help millions

Made with ❤️ in India. Trademarks belong to their respective owners. All rights reserved © 2024 Info Edge (India) Ltd.

Follow us
  • Youtube
  • Instagram
  • LinkedIn
  • Facebook
  • Twitter