What will you do if the site qty differ from Drawing qty

AnswerBot
1y

If the site quantity differs from the drawing quantity, I will take the following steps to address the issue.

  • I will review the drawings and specifications to ensure accuracy.

  • I will communicate with th...read more

ajwath mohammed
5mo
I will Compare the Completed and Original BOQ Quantity with the Engineer's Specifications and Drawing. if the construction team implements the construction as per the Engineers instruction and by the ...read more
srikanth reddy
1y

Payment will be made as per actual drawing measurements. Reasons for extra quantity will be find out & if found genuine it will paid as per norms

Prithiviraj Kasirajan
1y

In general it’s based on the contract conditions especially the order of precedence to be followed in case of dispute. However in most of the cases least of the two qty. will be certified and if there...read more

Lingaraja Ravi
1y

Find the root cause for that deviation and then get the solution for that. For example - Quantity deviated due to the wastage greater then allowable limit, rectify it from deduct the cost from concern...read more

Purushoth J
1y

We can't certified extra quantity first i find the route cause for extra quantity

Dasari.Haribabu
2y

Iam good technical skills at factory foundations and building constructions

Gnanasekar
2y

Will be check with  site incharge by site and will be add in  RA bill qty 

Add answer anonymously...
TCE Quantity Surveyor Interview Questions
Stay ahead in your career. Get AmbitionBox app
qr-code
Helping over 1 Crore job seekers every month in choosing their right fit company
65 L+

Reviews

4 L+

Interviews

4 Cr+

Salaries

1 Cr+

Users/Month

Contribute to help millions

Made with ❤️ in India. Trademarks belong to their respective owners. All rights reserved © 2024 Info Edge (India) Ltd.

Follow us
  • Youtube
  • Instagram
  • LinkedIn
  • Facebook
  • Twitter