What will you do when material is not received in time at site ?
I will assess the situation and take necessary actions to minimize the impact on the project timeline.
Check with the supplier for the reason of delay and expected delivery date
Evaluate the impact on t...read more
Think for alternative resource and Or alternative materials equivalent to this material accepted by the technology group.
First of all we'll have to look over our procurement schedules and the item of delivery.
If it's stopping the scheduled work we need to work on the post scheduled work and consistently chase for the de...read more
We should start the other activity, which material is available on site.
And intimate the procurement team for material still not yet received on site.
First I ask what is the problem