Plan vs progress percentage having negative variance, but updated schedule end date is not getting changed (later finish), why?

AnswerBot
1y

The progress percentage can be negative if the actual progress is less than the planned progress.

  • Negative variance indicates that the actual progress is behind the planned progress.

  • The updated schedul...read more

Asif Iqbal Umar
3y

If the Project Progress is based on cost, then in this case if the Actual Cost is more than the earned cost then the variance will be negative, however if the time taken to earn is same as plan then t...read more

Help your peers!
Add answer anonymously...
Nasser S.al-hajri & Partners Co.industrial Contractors Planning Manager Interview Questions
Stay ahead in your career. Get AmbitionBox app
qr-code
Helping over 1 Crore job seekers every month in choosing their right fit company
65 L+

Reviews

4 L+

Interviews

4 Cr+

Salaries

1 Cr+

Users/Month

Contribute to help millions
Get AmbitionBox app

Made with ❤️ in India. Trademarks belong to their respective owners. All rights reserved © 2024 Info Edge (India) Ltd.

Follow us
  • Youtube
  • Instagram
  • LinkedIn
  • Facebook
  • Twitter