Filter interviews by
Inquiring about the job profile.
posted on 28 Aug 2022
I applied via Referral and was interviewed in Feb 2022. There were 3 interview rounds.
posted on 4 Oct 2024
I applied via Recruitment Consulltant and was interviewed in Apr 2024. There were 2 interview rounds.
Yes, I am interested in joining the plant as a Senior Manager.
I have experience in managing teams and projects
I am excited about the opportunity to contribute to the growth and success of the plant
I am confident in my ability to lead and make strategic decisions
I have led cross-functional teams to successfully launch multiple products, resulting in increased market share and revenue growth.
Led cross-functional teams in product launches
Achieved increased market share and revenue growth
Implemented successful strategies for product development
Collaborated with stakeholders to drive project success
posted on 11 Dec 2024
Coding questions based on core Java and DSA
I applied via Naukri.com and was interviewed in Apr 2024. There were 2 interview rounds.
I applied via Campus Placement and was interviewed in Dec 2024. There were 2 interview rounds.
Multiple Choice questions concerning Mechanical, Metallurgy departments
posted on 24 Jun 2022
I applied via Recruitment Consulltant and was interviewed before Jun 2021. There were 2 interview rounds.
Question regarding Accounts knowledge
posted on 7 Mar 2021
I applied via Walk-in and was interviewed before Mar 2020. There were 4 interview rounds.
posted on 2 Jun 2022
I applied via Referral and was interviewed before Jun 2021. There were 3 interview rounds.
There are two types of cooling in transformers: oil-cooled and air-cooled.
Oil-cooled transformers use oil as a coolant and are typically used for larger transformers.
Air-cooled transformers use air as a coolant and are typically used for smaller transformers.
Oil-cooled transformers are more efficient at dissipating heat than air-cooled transformers.
Oil-cooled transformers require more maintenance than air-cooled transf...
Ohe fittings are used in overhead electrification systems to connect various components.
Tension clamp
Suspension clamp
Jointing clamp
Connector
Insulator
Earthing switch
Isolator
The procurement process involves several steps from purchase requisition to dispatch.
Purchase requisition is created by the department or individual in need of the goods or services.
The requisition is then reviewed and approved by the appropriate authority.
Once approved, the procurement team identifies potential suppliers and sends out requests for quotations or proposals.
Suppliers submit their bids or proposals, which...
posted on 16 Mar 2021
I applied via Recruitment Consultant and was interviewed before Mar 2020. There were 4 interview rounds.
based on 1 interview
Interview experience
based on 2 reviews
Rating in categories
Quality Engineer
14
salaries
| ₹1.8 L/yr - ₹3.6 L/yr |
Assistant Manager
13
salaries
| ₹5.2 L/yr - ₹10 L/yr |
Senior Engineer
10
salaries
| ₹4 L/yr - ₹5.4 L/yr |
Production Manager
10
salaries
| ₹9.9 L/yr - ₹12.4 L/yr |
Senior Production Engineer
9
salaries
| ₹3.2 L/yr - ₹5.4 L/yr |
Jindal Group Of Companies
Ms Agarwal Foundries
Patton International
Shri Mahavir Ferro Alloys