what is the procedure for form work removal on site?
AnswerBot
1y
The procedure for form work removal on site involves several steps to ensure safety and quality of the structure.
Inspect the concrete for strength and stability
Remove the formwork in a systematic mann...read more
AHAMAD KHAN PATHAN
7mo
First we need to remove side face shutter . Second we need plan shutter are removed. At final we need remove prop support of primary and secondary beams 1.Vertical formwork of wall, column and beam- 1...read more
Krishnamoorthy.p
1y
First deshuttering the beam side and then remove the slab shuttering board's . After this remove the beam bottom shuttering and need to fix back props
kabir8817k
2y
ex -
PrimeTech builder and Contractor
24 to 48 hours for column and Bimb except bottom
and 21 days for saleb
KABIR ANAND
2y
ex -
PrimeTech builder and Contractor
24 to 48 hours for column and Bimb except bottom
and 21 days for saleb
Add answer anonymously...
Top Larsen & Toubro Limited Graduate Engineer Trainee (Get) interview questions & answers
Popular interview questions of Graduate Engineer Trainee (Get)
Top HR questions asked in Larsen & Toubro Limited Graduate Engineer Trainee (Get)
>
Larsen & Toubro Limited Graduate Engineer Trainee (Get) Interview Questions
Stay ahead in your career. Get AmbitionBox app
Helping over 1 Crore job seekers every month in choosing their right fit company
65 L+
Reviews
4 L+
Interviews
4 Cr+
Salaries
1 Cr+
Users/Month
Contribute to help millions
Get AmbitionBox app