How many workers would you engage for 1 cum concrete? How much binding wire would you require for binding 1MT reinforcement. How much can you negotiate while procuring materials?
AnswerBot
1y
The number of workers for 1 cum concrete depends on the project timeline and equipment used. Binding wire requirement for 1MT reinforcement depends on the binding pattern. Negotiation while procuring ...read more
Anonymous
3y
8 workers. 8kg/MT. Upto 20% depending upon materials.