Q1. what is first step you will do when you see a secondary core of ct open and feeder still working on very less load?
The first step would be to investigate the cause of the secondary core of ct being open while the feeder is still working on very less load.
Check for any loose connections in the secondary core of ct
Inspect for any damage or faults in the secondary core of ct
Verify the load on the feeder to ensure it is within normal operating range
Consult with colleagues or experts for further troubleshooting steps
Q2. what is high voltage testing standard as per IEC?What will be testing voltage for 33kv system voltage.what testing kits your familiar to work on??
High voltage testing standard as per IEC includes testing voltage for 33kV system and familiar testing kits.
High voltage testing standard as per IEC includes IEC 60060-1 for high-voltage test techniques.
Testing voltage for 33kV system voltage is typically around 70-80kV.
Common testing kits for high voltage testing include insulation testers, voltage detectors, and partial discharge testers.
Q3. what is LIBBP,HIBBP Stability and sensitivity ?how you will impliment logic for one incomer and three outgoing feeders?how u will do BBP protection testing for this system ?
LIBBP and HIBBP stability and sensitivity refer to protection schemes for electrical systems. Implementing logic for one incomer and three outgoing feeders involves setting up coordination and communication between devices. BBP protection testing ensures the system operates correctly under fault conditions.
LIBBP and HIBBP stability and sensitivity are important for ensuring reliable protection of electrical systems.
Implementing logic for one incomer and three outgoing feeders...read more
Q4. what is ATS ?how you will configure ATS relay?what is trip selection.
ATS stands for Automatic Transfer Switch. It is used to automatically switch between primary and backup power sources.
ATS is a device used to switch between primary and backup power sources in case of power failure.
To configure ATS relay, you need to set the parameters such as voltage, frequency, and delay timings.
Trip selection refers to the setting that determines when the ATS will switch between power sources based on certain conditions.
Examples of trip selection criteria ...read more
Q5. what is close block?why its necessary?why no fuse or mcb ON CT CIRCUIT?
Close block is a device used to short circuit the secondary of a current transformer (CT) during testing to prevent damage to the CT. No fuse or MCB is used on the CT circuit to avoid any interruption during testing.
Close block is used to short circuit the secondary of a CT during testing to prevent damage.
It ensures that the CT is not overloaded with excessive current during testing.
No fuse or MCB is used on the CT circuit during testing to avoid any interruption in the curr...read more
Q6. how much years of experience you have in substation network?
I have 5 years of experience in substation network.
I have worked on various substation projects, including design, testing, and commissioning.
I have experience with different types of substation equipment and systems.
I have successfully completed multiple substation network projects on time and within budget.
Q7. what you know about alfanar saudi arabia ?
alfanar Saudi Arabia is a leading electrical engineering company in the Middle East.
alfanar Saudi Arabia specializes in electrical engineering solutions.
They offer a wide range of products and services including power distribution, control panels, and lighting solutions.
The company has a strong presence in the Middle East and has completed numerous projects in the region.
alfanar Saudi Arabia is known for its quality and reliability in the field of electrical engineering.