Complete Process of tower foundation day by day.
AnswerBot
1y
The process of tower foundation involves several steps that are carried out day by day.
Day 1: Site preparation and layout survey
Day 2: Excavation for foundation
Day 3: Reinforcement placement
Day 4: For...read more
Anonymous
4y
As per specifications, First day excavation, second day dressing and compacting, third day steel binding for raft, fourth day shuttering and casting of raft, fifth day first lift of Column casting, si...read more