Q1. What is complete process of cross country pipeline project from starting to ending?
The complete process of a cross country pipeline project involves planning, design, construction, testing, and commissioning.
Planning phase: Identify project objectives, route selection, environmental impact assessment.
Design phase: Engineering design, material selection, pipeline alignment.
Construction phase: Clearing and grading, trenching, welding and joining, coating and insulation.
Testing phase: Hydrostatic testing, non-destructive testing, leak detection.
Commissioning p...read more
Q2. What is hydrotest of pipeline & what we are checking through this test?
Hydrotest is a pressure test conducted on pipelines to check for leaks and structural integrity.
Hydrotest involves filling the pipeline with water and pressurizing it to a specified level.
The pressure is maintained for a specified duration to check for leaks or any other defects.
The test also checks the structural integrity of the pipeline by measuring the amount of deformation under pressure.
The test is usually conducted before commissioning the pipeline to ensure its safety...read more
Q3. What is steps of hydrotest & which equipment and instrument we are using?
Hydrotest involves filling the equipment with water and pressurizing it to check for leaks or defects.
Equipment is filled with water and pressurized to a specified level
Pressure gauges are used to monitor the pressure
The equipment is held at the specified pressure for a set amount of time
After the test, the water is drained and the equipment is inspected for leaks or defects
Equipment and instruments used include pumps, hoses, pressure gauges, and safety valves
Q4. What are the major defects of welding how we element them?
Major defects in welding and how to eliminate them
Porosity
Incomplete fusion
Cracks
Undercutting
Lack of penetration
Contamination
Improper electrode storage
Proper welding technique and equipment maintenance can eliminate most defects
Q5. What instrument using in joint coating process and acceptance criteria of surface roughness?
The instrument used in joint coating process is a profile gauge. Acceptance criteria for surface roughness is specified in the project specifications.
Profile gauge is used to measure the surface roughness of the joint coating.
Acceptance criteria for surface roughness is specified in the project specifications.
Surface roughness is measured in microns or mils.
Surface roughness should be within the specified range for the joint coating to be accepted.
Q6. What is difference between WPS, WQT, PQR, PQT?
WPS is a welding procedure specification, WQT is a welding qualification test, PQR is a procedure qualification record, and PQT is a performance qualification test.
WPS is a document that outlines the welding process to be used for a specific job
WQT is a test that ensures the welder is qualified to perform the welding process outlined in the WPS
PQR is a record that documents the results of a welding procedure qualification test
PQT is a test that ensures the welded product meet...read more
Q7. What are cods and standards follow for laying pipeline?
Various codes and standards are followed for laying pipelines to ensure safety and quality.
API 1104 - Welding of Pipelines and Related Facilities
ASME B31.4 - Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids
ASME B31.8 - Gas Transmission and Distribution Piping Systems
ISO 13623 - Petroleum and Natural Gas Industries - Pipeline Transportation Systems
DOT Pipeline Safety Regulations - 49 CFR Parts 192 and 195
Q8. What is role of vent pipe in cased crossing?
Vent pipe is used to equalize the pressure inside and outside the casing during installation of pipelines.
Vent pipe is installed in the annular space between the carrier pipe and casing.
It helps to prevent the formation of a vacuum or pressure differential during installation.
It also allows for the escape of air or gas trapped in the annular space.
Vent pipe should be installed at the highest point of the casing.
It should be capped after installation to prevent debris from ent...read more
Q9. How to check disbondment in cold bend pipe ?
Disbondment in cold bend pipe can be checked using visual inspection, ultrasonic testing, and radiography.
Visual inspection can detect disbondment on the surface of the pipe.
Ultrasonic testing can detect disbondment in the pipe wall by sending high-frequency sound waves through the pipe.
Radiography can detect disbondment by using X-rays or gamma rays to create an image of the pipe's internal structure.
Disbondment can also be checked by performing a bend test on the pipe and e...read more