Without doing anything people are getting salary for last 22 months for SCTP project at abudhabi ....our last client meeting happened in Feb 2016 then after hardly 1% project progress with last 22 month time and our client stoped to ask about project ...no more meeting with client....particularly from August 2017 to till now project people sitting in essar villa not entered to site for execute the job....just to convince company top management the entire project crew showcasing by sending some man power to site ...again no progress ....losing money one side and other side from Project team is geeting salary by sitting idle.....the great wishes to the great Project Manager of Sctp. Against project allotted value now essar spent 200% still project not completed which will take another 18 months time if they need to completed 100% ...this is one of the great achievement of very very skilled project manager and Co. ..