Timeline for PEB structure from concept to operation

AnswerBot
7mo

The timeline for a PEB structure from concept to operation varies depending on factors like size and complexity.

  • Initial concept and design phase

  • Obtaining necessary permits and approvals

  • Fabrication and...read more

Anonymous
author
1y
Concept to design conclusion - 15 days Boq, budget, scheduling & process - 15 days Tendering and vendor onboarding - 45 days Procurement - 30 days Peb installation - 45 days Finishing & handover - 45 ...read more
Help your peers!
Add answer anonymously...
Tata Projects Regional Manager South Interview Questions
Stay ahead in your career. Get AmbitionBox app
qr-code
Helping over 1 Crore job seekers every month in choosing their right fit company
65 L+

Reviews

4 L+

Interviews

4 Cr+

Salaries

1 Cr+

Users/Month

Contribute to help millions
Get AmbitionBox app

Made with ❤️ in India. Trademarks belong to their respective owners. All rights reserved © 2024 Info Edge (India) Ltd.

Follow us
  • Youtube
  • Instagram
  • LinkedIn
  • Facebook
  • Twitter