
How many days will be taken in construction of an underground rcc water tank of 5x5 x2 m

AnswerBot
8mo

The construction of an underground RCC water tank of 5x5x2m can take approximately 30-45 days.
The time taken for construction can vary based on factors like soil conditions, weather, availability of m...read more
Anonymous
7mo

M30
Abhay Srivastava
7mo

M30
Mayank Chandra Patel
5mo

M30
Anonymous
5mo

35-40 days
Ravindra M
7mo

M30
Yugdeep Goregaonkar
7mo

Approx 35~40days
Add answer anonymously...
Top UltraTech Cement Assistant Manager interview questions & answers
Popular interview questions of Assistant Manager
Top HR questions asked in UltraTech Cement Assistant Manager
>
UltraTech Cement Assistant Manager Interview Questions
Stay ahead in your career. Get AmbitionBox app
Helping over 1 Crore job seekers every month in choosing their right fit company
65 L+
Reviews
4 L+
Interviews
4 Cr+
Salaries
1 Cr+
Users/Month
Contribute to help millions
Get AmbitionBox app